Hi Experts,
I defined Block Planning for the FERT that are produced in a plant and I have the following 2 questions about Block Planning:
1) Block Planning can be used in APO SNP?
I see only the "Block Planning Class" in PPDS PDS, I have read that I can used Block Planning in APO SNP, but I do not know how I can do
2) If I execute the following 3 steps:
a)SNPHeuristic, it generates SNP:PL_ORD of FERT and HALB (if halb is produced in the same plant), it generates PurRqs of HALB (if halb is produced in other plant) and ROH
b)ConvertSNP:PL_ORD to PlOrd, the system changes the date of PlOrd of the FERT according to the blocks defined in the resource, but does not change the PlOrd of the HALB (if halb is produced in the same plant) and PurRqs of HALB (if halb is produced in other plant) and ROH
c)PPDS Optimizer, the system changes the date of the PlOrd of the FERT according to the blocks defined in the resource to remove the heavy workload of the resource, but it does not change the date of the PlOrd and PurRqs of the components
What should be done to change the date of the PlOrd and PurRqs of the components according to the PlOrd of the FERT?
Best Regards,