Hi All,
I have a issue against target day of supply within PP/DS horizon, hope someone can help me.
Background Setting up:
PP/DS horizon:150days
SNP Horizon: 150Days
Target day of supply : 65 Days;
Independent demand (Forecast): 1M / week;
When i run SAP_PP_002 PP/DS Heuristics, system works well at first a couple of weeks. But there are no PP/DS planned order at last 5 buckets which should be base the target days of supply.
If i manual create a huge demand, let's say 10 Million at end 1st June. The planned orders will be generated after run SAP_PP_002 heuristics.
"
Target Days' Supply in Workdays
Use
Use in Production Planning and Detailed Scheduling (PP/DS) and Supply Network Planning (SNP)
The PP/DS standard heuristic SAP_PP_002 (Planning of Standard Lots) and the SNP heuristic take into account the target days' supply if you have selected the target stock level methodTarget Days' Supply from Product Master (' '), Maximum from Maximum Stock Level/Target Days' Supply (5) or Total from Maximum Stock Level/Target Days' Supply (6).
Dependencies
The SNP optimizer ignores the target days' supply.
"
Can anybody help me ?
Thanks.