Hi Gurus,
I am having a problem doing multi-level scheduling. I have parametrized a scheduling profile in the Planning Board which takes the operations level by level (from semifinished to finished product) and schedules them doing FindSlot and ForwardScheduling.
Problem is that setup activities get separated from production activities of the same operations at the level just after the bottleneck, somehow the system does not consider that setup and production MUST be done one exactly after the other.
Is there a way to enforce this at the routing level / resource level (which I am currently missing and I always gave for granted), or this is a bug and I should open an oss note.
best regards,
J.