Dear colleagues,
We have 3 production lines, 2 press-forms and 1 setup-engineer. 3 productions lines X 2 press-forms = 6 combinations.
Press-form can be installed to any production line.
Productivity depends on the production line and press-form combination. Only one press-form can be installed on the production line.
Work hours of production lines and press-forms for production planning - 24 hours a day, 7 days a week. Setup matrix is use properly.
Setup activity can be performed only by a setup-engineer (work time at 9-00 to 14-00). In another time changeover can not be performed.
Production line and press-form loaded simultaneously during the entire period of production and can not be used to produce another product.
Questions:
1) How PDS should be structured in APO PP/DS in order to reflect abovementioned requirements?
2) How to plan setup activity only in work hours of setup-engineer?
Best regards, Dmitry