Setup activity and alternatives modes in APO PP/DS

$
0
0

Dear colleagues,



We have 3 production lines, 2 press-forms and 1 setup-engineer. 3 productions lines X 2 press-forms = 6 combinations.

Press-form can be installed to any production line.

Productivity depends on the production line and press-form combination. Only one press-form can be installed on the production line.



Work hours of production lines and press-forms for production planning - 24 hours a day, 7 days a week. Setup matrix is use properly.

Setup activity can be performed only by a setup-engineer (work time at 9-00 to 14-00). In another time changeover can not be performed.

Production line and press-form loaded simultaneously during the entire period of production and can not be used to produce another product.



Questions:


1) How PDS should be structured in APO PP/DS in order to reflect abovementioned requirements?

2) How to plan setup activity only in work hours of setup-engineer?




Best regards, Dmitry