Hi experts
We have an issue in aggregated planning, hope you could help us.
Background:
Material A Plant 1000 -> Plant 1200 ->Sales
Material B from 2000 -> Plant 2200 ->Sales
Plant 1200 and Plant 2200 is the same physical location (it is one Port which have the capacity constraint of Load-in and Storage).
We aggregated Location 1200/2200 to 3000 hierarchy.But Product is in A, B is same material code of Header product A, B level 001, to avoid the complication.
We have three resources: handling in, and storage assign to 3000 and transportation resource in T-lane. (1000 to 3000, 2000 to 3000)
The Optimizer happens in Material A, B 1000, 2000, 3000. It works fine in that level.
After Optimizer we check the resource consumption, the disaggregation also works fine, the STR creates in 1000 to 1200, and 2000 to 2200, based on the hierarchy and net demand.
Issue:
We need these Capacities consumption load from planning area into the reporting.
If I chose Delete in Aggregated level in /sapapo/snp06 , the resource consumption will be lost for the handling and storage resource.
I choose: Do not change “agg” level, during disaggregation.
It duplicated the distribution demand in 1000 plant because now both 1000 to 1200 and 1000 to 3000 STRs exist in SNP book in 1000 plants
Appreciated anyone could suggest to solve this issue, thanks a lot.
Thanks James.