Hello Gurus,
Earlier we had 2 ECC systems in the landscape.
Purchase requisition A from APO system supposed use RFC destination 1 and reflect in Plant XXXX
Purchase requisition B from APO system supposed use RFC destination 2 and reflect in Plant YYYY
Now we have only 1 ECC system in the landscape. we have changed the publication settings accordingly. but preq still not getting transferred correctly to ECC system.
Debugging the code shows system trying use wrong RFC destination.
Is there any other configuration setting we are missing.
Please advise.
Thanks In Advance
Shyam