Hello,
We have product P1 with forecast values for next 12 months. We added a phase out profile recently to phase out this product after June 2014. In phase out profile, we enabled the "After end date, apply constant factor" as "0%".
In planning area, we have the forecast setting to store the "corrected forecast" in a separate key figure.
When a univariate is run for this product, we see forecast values, "corrected forecast" values till June 2014 only, which is correct, but when i save them, the corrected forecast values are copied till June 2014 only and values after June 2014 in Planning Book remain as such. They are not cleared out.
I tried clearing the "corrected forecast" manually and ran again, but still the values somehow got populated again beyond phaseout period. There are no macro's affecting this KF.
Any light thrown on this would be appreciated.
Thanks!!