Hi Guys,
My PP/DS team is facing an issue wherein on some respurces when they create a Pl order inside the PP/DS horizon, the system tries to schedule the orderas sson as it is created. In case the planning board is full it does not even create the order. On some resources it creates a pl order inside the horizon without trying to schedule the same. In some rear cases it creates a pl order at the end of the horizon. I think it may ahve to do something with the resource level setting and looking into it.
Any input would help greatly...
Thanks,
Subash