CTM Continuous Planning must have 24 hr. utilization for Resources

$
0
0


I am trying to generate a CTM plan using Continuous planning and SNP type sources of supply.

I find that the process only allows resources that have 24 hour utilization.

Any Breaks, or less hours per day will generate an error in planning.

 

If I set the utilization to less than 100%, CTM will still generate orders for the full 24 hours.

So, the capacity of the resource will be exceeded.

 

I am wondering if there is a way to allow CTM planning to plan with reduced time per day in planning.

 

Regards,

Roger Weinberg