Hi,
I need one clarification for PP heuristic run in APO.
I have set PPDS horizon as 2 days in material master.
Lot size procedure by period 1 W
Demand at DC are
D1 D2 D3 D4
10 20 30 40
My expectation that PP will only consider the demand in PP horizon and will generate 10+20=30 purchase req whereas i am getting output as 10+20+30+40=90(adding all demand in 1 W)
Please suggest if this is correct behavior.
Thanks,
Krishna