Planning Book to display SNP Planned Order Start Date

$
0
0

Hi ,

 

Am using SNP Heuristic to run the MRP in APO.

After Heuristc run we generally see the planned orders in the bucket corresponding to end date of the planned order.

 

For e.g

 

Qty = 100

 

Rqmnt Date = 10.03.2014

 

GR Processing TIme = 4 days

 

Planned oRder Qty of 100 is visible on 10.03.2014 but when the user goes to Capacity Planning View then teh capacity consumption is visible on

06.03.2014.

So User gets confused as the PLanned Order qty is shown on 10th and the capacity consumption is on 06th.

My requirement is can we show the qty of 100 in the planed oRder start date instead of planned order end date.

In my e.g it would be 06.03.2014 so the capacity consumption and the planned order qty will be visible on the same day.

 

 

REgards,

 

Raj