Hi all,
I'm trying to CIF a SNP PDS from ERP to APO.
The PDS always shows up in APO with a generated operation (from planned delivery time).
Any idea why it does not pick up the real operation from the routing?
For another material/plant same procedure works fine.
I made the following checks:
- Integration model exist for material, PDS, ressource
- Production version exists
- Validity dates in routing / PV are ok
- Operation has machine time maintained
- After deletion of PDS and re-ciffing the PDS it sill shows up with a generated operation
Thanks for any advice.
Regards,
Daniel