Hello Experts,
We would like to achieve below scenario through CTM PPDS planning.
Scenario:- While completing production of entire quantity of one level bom
next level bom production should started.
At lower level BOM we need to produce 200 units, but before completing 200
units(suppose we have produce 100 units),
next upper level BOM production should get started.
Hence this is overlapping of BOM level production. This is not overlapping
of operations.
Do you know how this can be achieved CTM PPDS planning.
|
|
|
|
200 |
| BOM level"A" | |
| 200 | BOM level"B" | |
|
|
|
|
Thanks for your help.
Best Regards
Abhimanyu