Afternoon all,
I am having trouble transport planning using separate trucks and trailers in 9.1 and get the message 'Best solution is not to deliver any freight units that can be planned'. Using a single vehicle resource with capacity works no problem. The message also appears instantly even though the optimizer run is set for 60 seconds.
This is the customizing I've performed :-
Defined 2x means of transport
A truck - multiresource (no of = 100), Your Own MTr, No Capcity, GIS Quality
A trailer - Your Own MTr, Passive, GIS Quality
(Why can't a passive MTr be a multiresource?, how do you tell TM how many there are available?)
defined 1x MTr combination using 1 of each MTr from above
defined 2x resources
The truck with location, MTr, factory calendar, zero capacity
The trailer with location, MTr, factory calendar, capacity
defined both new MTrs in the planning cost settings of the planning profile
defined transportation lanes for both MTRs (not sure if I need to do that as I noticed only one for the truck gets sent to the optimizer, unless that is the problem?)
defined both truck and trailer in the capacity selection I am using for the cockpit.
Any suggestions/help you can give me would be a great help.
Thanks
Steve