APO gurus,
Production Planning Run occurs in APO against valid PDS. Some of PDS have Min/Max Lot sizes.
However, in the non assembly, the system bahaves with a lot for lot procedure. We get planned orders being created outside the Min/Max lot Size set in PDS, and get planned order covering the exact requirment, which is exactly what we want, but planned orders created are not referring to any PDS. This resuls in planned orders witout output (components) which causes us some issues in term of demand on dependent requirements.
Is there any enhancement point that would allow the "BOM selection", without creation in ECC/APO a specific BOM/PDS without opeartion and lot size range. ECC behaves like that when no valid production version is set, BOM is selected.
Thanks upfront for your feedback.
Regards