SNP Planning Book
I have entered manually the Production Plan in the "production planned". Extended stock horizon is fixed to 18 months. The source of supply is not prompted. PDS selection is not prompted when saving the planning book. We are manually entering figures that does not match the batch size. Example Batch size is 10,000 but we are manually planning a production of 100,000 each or 10 batches.