Hi
now trial MRP run is conducted in PPDS but, i want the same to be conducted in R/3 .....because PPDS mrp run is not working effectively ...so I am thinking in terms of why do not try it in R3 ?.....only difference is -in PPDS product and resources will be planned simultaneously....whereas we have to take two steps in R3 -like MRP run first in MD01 and take the planned orders in capacity planning table and do resource planing there...am i rite??? would like to have expert suggestion ??
to go ahead what should i do ? now MRP type is X0 so i need to change it to PD and continue with ECC rite?? i need suggestion from you experts before taking this from APO to ECC.
because my management wants some kind of MRP run as soon as possible and later improvise on it.step by step.
Thanks