Hi Experts,
I am trying to model Furnace as the Multi activity resource in PPDS and here are my requirements.
I want to use Volume as one dimension and time as the other dimension. I know, we can set Volume as a dimension in APO Resource master.
I need some guidance on how to setup the routing for this resource and how to make PPDS to schedule on these 2 dimensions Volume and Time.
For example, I have a material which has a volume of 1 FT3, and it has to be heated for 6 hrs on the furnace. The furnace has a capacity to handle maximum of 10 FT3 at a time. How to model this in the PDS?
Any pointers to model this requirement would be really appreciated.Thanks.
Regards,
Manimaran M.