Deployment heuristic

$
0
0

Hi,

I have a question regarding the logic of deployment heuristic.

 

We run SNP heuristic weekly on Sundays in weekly buckets and deployment heuristic Sunday - Thursday night.

 

In my example there is deployment stock order in week 32 with 68.400 PC. When I run the deployment heuristic in snp planning book with settings, delete snp orders and real time (not referring to last snp run), the deployment stock order disappeared.

snp issue 1.png

 

I checked then the three distribution centers we ship this product to and saw that two of them are fine, still above the defined 20 days of supply but the third location dropped down to 6 days of supply tough this product has 21 days of supply in product master data in that location.

 

 

Question: Is the deployment heuristic not considering at all at the stock situation at the receiving plant?

 

If not, what is the distribution heuristic logic / what does it consider?

 

thank you in advance for your input!

 

best regards,

Pilvi