Dear Gurus,
After I run the SNP heuristics in APO, I got some planned orders in planning book. But when I check MD04 in ECC, I found real planned orders are generated (There is no such order before I run the SNP heuristics), And from the action date/time and the action APCR, I know ther are newly generated.
When I run CCR afterwards, I can see those planned orders shown as difference in content, but no matter I wanted to push those to APO from ECC or the opposite way, nothing happened. (CQ are cleared before CCR.)
Really appeciated for your answer. I'll give points.
BR,
Yang