Hello,
My scenario is that we use Stock Transfers using RBATP. I want to maintain a picking time of i.e. 2 days at the sending plant to prepare and process the shipment. I use the transportation lane to determine the time between plants. And I use the unloading time to cater for the time to putaway etc at receiving plant.
- Condition PICK has a 24 Hrs
- Transportation time on Transportation lane has 72 Hours
- Condition UNLD has 36 HRS
In the analysis of the Scheduling Results and log, everything appears to be correct.
this MAD is not transferred to the the schedule line in the sales order:
But the created STR is close:
How can I get the sales order schedule line to reflect picking time, transportation and unloading times?