Hello,
Here is a strange issue that we are having. In PO line item (in ECC) the schedule lines are like below
Schedule line ID Quantity
1 100
2 200
3 300
It goes to SNC and user opens this PO.. all looks ok. After clicking on change , Confirm (PO item) , Save and then Publish. The data reflected on ECC is in reversed order. But the confirmation tab has the same old sequence.
Schedule line ID Quantity
1 300
2 200
3 100
Has anybody seen this issue? Any suggessions?
PS: There are no user exits or BADIs for any custom logic for processing all the interfaces between ECC - SNC.
Thanks,
Amit.