Hi,
I have a scenario wherein the client is manufacturing cakes, so am planning the Finished goods (i.e FG1) of cakes in APO with MRP type X0.Its SFG which is Base Cake is also planned in SNP since it is a critical component.NOw the client also gets demand for Make to ORder cakes whoose material code is different than the normal cake being planned in APO.So this MAke to ORder (i.e FG2) cake is being planned using strategy 40 and mRP type "PD" and based on sales order.
But the SFG is the same Base cake which is planned in APO.
my problem is dat this requirement from the FG2 goes as dependant requirement to SFG but it does not create any planned orders for Sfg AS IT HAS mrp type X0, also the dependant requirement does not get transferred to APO so this reqmnt is not planned in APO as well.
My question is can we transfer this dependant requiremnt of SFG to APO.
Thanks in adavnce.
REgards,
Raj