A product is sourced by store S001 from Regional DC R001. In product master for S001 I specified procurement type as F and PDT = 14 days. Also maintained the transportation lane. When I run either SNP or PPDS Heuristics, in either case the PDT is not considered during the run.
By that I mean if a preq is required on May 20th in S001 the Preq Rel date in R001 should appear as May 14th. However the PDT is being ignored and the dates appear exactly the same in both locations.