Hi,
I am trying to model the following scenario in PPDS.
Plant P100
Product A - Order 500 units (Date 05/15)
Product B - Order 40 units (Date 05/15)
Resource Capacity - 100% - 200 units per day
When I execute a PPDS run, Product A should utilize only 90% of capacity of resource per day and 10% by Product B. How can i achieve this?
Master Data:
Resource - NO PPDS bucket capacity, Finite capacity is Time-Continuous with 100% utilization rate.
PP/DS PDS, no setup time.
In-House Production, No Procurement
Finished goods and components, PDS exist at Plant P100.
I have modeled something similar using the PPDS Optimizer to restrict capacity utilization by a set % of utilization rate maintained in the resource, but executing optimization or scheduling takes place at resource level and I do not see any kind of filter to restrict by products. The optimizer resulted in using 90% of capacity for both Product A and Product B combined.
Appreciate your inputs.