Combine Lot-for-lot Procedure and Periodic Procedure

$
0
0


Hello all,

 

For some of our products to be purchased, we want to combine both procedures in the Lot-Size procedures of the product:

- Lot for lot procedure

- Periodic procedure

 

What do we want to accomplish?

After having done an Optimzer, we want to run the heuristic SAP_PP_002 to create requisitions and then we want to execute a fix pegging so that the requisition is reserved for that specific production order (one on one relation between the production order and the requisition).

 

When running a Planning of Standard lots (Heuristic SAP_PP_002) in the planning run we should be able to respect the lotsizes as required for each production order and at the same time the requisition should be available on Tuesday or Friday during that week.

 

When I set up the Lot for lot procedure, and I run the heuristic, I get requisitions with the exact lot size as required for the production order (most of the times 1 pc, sometimes 2 or more ...) but then I cannot force them to be available on these Tuesdays or Fridays. When I use the Periodic Procedure, I have the requisitions available on the defined dates according to the planning calendar, but it groups all the requirements into 1 requisition per period. With this result it's not possible to have a 1 on 1 relation between the production order and the requisition.

 

Anybody having any suggestion?

 

Thank you!

Philippe