Hi experts,
I have the following case, to produce the FERT001 I need to consume ROH001 or ROH002, for this reason I have two PDS one with ROH001 and one with ROH002
When I execute PPDS heuristic the system generates production order for FERT with the PDS ROH001, but if on the date that the order will be executed I do not have availability ROH001 I need that the PPDS Heuristic or OPTIMIZER changes the PDS and takes the ROH002
Is this possible?
How I can do?