Dear colleagues,
We have a multi-level production process, repetitive manufacturing, PP-REM, up to 6 levels of BOMs.
Finished and semi-finished goods can be produced on alternative resources and can have different BOMs.
Alternative modes are maintained as alternative sequences in a routing (CA01).
Different production versions(PDS) are created for different BOMs.
We need to create a feasible multi-level production plan which includes:
- raw materials planned delivery time
- workload of main and alternative resources (finite scheduling)
- removal of backlog
Could you please give me an example of heuristics to be used in the planning run /SAPAPO/CDPSB0 ?
Thank you in advance for your help.