Hi,
We e-explode orders in APO. We have alternative resources in the order and the order is scheduled in any one alternative resource.
When order is getting re-exploded then the order is shifted to primary resource from the alternate resource.
I need to retain the resource in order even after re-explosion.
This is not hapenning with retain modes functionality in our case since we use PDS with dummy resource.
Require code/ badi/ exit, where we can influence resource in order while scheduling.
Please give some inputs.
Thank you in advance.
Regards,
Surajit Das