I have the following scenario where CTM is generating Late SNP Planned orders (~ 82 days late) even though there is available capacity starting today on all resources ( valid -30 days +180 Days, used capacity lengthen as well). Stock is available for all the components immediately. The quantity of the SNP Planned Orders generated are correct and are consistent with capacity as well but the start date is incorrect.
In-House Production ( No T-Lanes, Only SNP PDS)
Finished Product A SNP PDS
43 Operations ( each operation takes a day)
Activity relationships are consistent
Bucket Resource consumption has a value for all modes of each activity
Resource Parameters
Start Time: 00:01:00
End Time : 23:59:00
100% Utilization Rate
SNP Bucket Capacity from Continuous capacity
No Downtimes
CTM Parameters
Time Stream: 02/14/2015 - 11/08/2017 (Days)
Replan All orders
Delete Orders that are not Firm
Backward Scheduling
Fixed Pegging
Keep Lateness to Minimum
Plan all resources finitely ( resource has Finite Scheduling set as well)
Demand Prioritization by 'MDBAT' - Material Availability date
Bucket Oriented Planning
SNP Prder
SNP PDS Type
Nothing is excluded in master data and Procurement Alternatives
All I have is a sales order for 04/21/2015 for 4000 Units and enough stock on components to create an order of 710 units. After the CTM run, start date of order is 07/05/2015 and end date is 08/16/2015. I am fine with the duration taken for order creation but the start date should have been today's date i.e. 04/15/2015.
There are no down times on capacity and standard capacity is used. Checked the factory calendar as well(its fine) and no calendars on location.
I have activated explanations in the log.
Capacity is available on all 5 resources from 03/03/2015 to 11/08/2015
An Interesting Find
Warning in todays Explanation Log -
Activity 036000000030 036000000030P: Dispatch not possible from 04/15/2015 00:00:00 to 04/21/2015 07:00:00 |
Activity 036000000030 036000000030P / Mode 1 cannot be scheduled |
Warning in Yesterdays Explanation Log -
Activity 035000000028 035000000028P: Dispatch not possible from 04/14/2015 00:00:00 to 04/21/2015 07:00:00 |
Activity 035000000028 035000000028P / Mode 1 cannot be scheduled |
I see that the warning has changed to the next operation of SNP PDS since yesterdays Run.
I would really appreciate any suggestions or directions to find root cause.