Hello Experts,
Another question.
Have maintained a safety time on a material of 12 days supply. We are running SNP Heuristics and system is creating purchase reqs, however the reqs are not being created early enough to support the required 12 days of supply. The first Purchase Req is created with a date 3 weeks after the Days supply drops below the desired 12 and looking out to the future it never recovers.
When we review the reqs that SNP created in ECC I can see that MD04 is telling us to reschedule in the reqs to the date that I would expect.
Safety Days supply is maintained in APO on the Product Master and is also present in ECC on MRP Views.
Why is SNP not creating the reqs on the correct date? We do not have a production horizon that would be impacting this.
There is no PDT that would be pushing it out either.
Any ideas?
Thanks