Hello All,
I'm facing following issue where SNP PReqs are created in advance or well before lead time.
Demand is in September 06 2015 for qty:2182
total lead time is 50 days
Expected start date to be around 13th July 2015
but heuristic is planning this demand for two different quantities as follows;
Qty 1870 to start on April 22nd 2015 and Qty 312 to start on April 29 2015
I have checked all planning relevant calendars (factory & TS calendars) they are fine. No holidays, no downtimes etc.
No min or max lot size defined in MAT1.
What could be the reason for this behaviour?
Any suggestion/help is much appreciated.
thanks.