Multiple PDS selections during SNP Heuristic Run

Hi,

 

I am testing this scenario. I have created the 2 production versions in ECC and transferred to APO. In APO 2 PDS generated based on ECC production versions.

 

Now I created PIR's in APO and executed the SNP Heuristics, Production version is taking consideration and creating the SNP planned orders and dependent requirements, For production version 2 SNP planned orders generating and there is no Dependent demand.

 

If I change the source of supply manually in SNP planning book, dependent demand is generating for production version 2 SNP planned orders.

 

My question is any possibility to SNP Heuristics generate SNP planned orders and dependent demand for Production version 1 & 2 without manual changes in SNP planning book, because SNP planned should not change the source of supply manually and it is time taking effort.

 

Regards,

Lingaiah