Hi gurus,
We're using the PP/DS Optimizer to finitely plan one of our location, works fine up to now but we'd be interested to finetune strategy per resources DURING the optimization (meaning not after the optimization run through dedicated heuristics for instance).
Basically the requirement would be to apply a different strategy (Backward scheduling or Compact scheduling) per resource during a single optimization run, for instance: resources R1 & R2, optimize at the same time:
- R1 with Compact scheduling
- R2 with Backward scheduling
Selection of resources beeing done "outside" the optimization profile, would there exist a possible way or an alternative way to achieve such a requirement? (even through Badl/enhancement if not feasable in standard)
Thanks in advance for your feedback or return of experience!
Regards,
Pascal.