creating customer specific deployment reqs.

$
0
0

Hi

Our supply network has a DC that is sourcing from a plant. The demand at the DC is at location-product-customer level in DP. We are releasing to SNP/PPDS with location as a descriptive characteristic. So far so good.

We want to run a SNP or PPDS planning runs so that the demand from DC is carried to the plant, a planned order at the plant as needed and then deploy that stock to DC in deployment run at the customer level.

What this means is at end of the planning runs, we want deployment reqs. that are specific to each customer and not one single qty. for all customers.


Example:

We have DC1 where we have material M1 and 3 customers C1, C2 and C3

Forecast in DP:

M1, DC1, C1 has 100 CAR

M1, DC1, C2 has 150 CAR

M1, DC1, C3 has 200 CAR

 

The forecast is released to SNP/PPDS at the material-location-customer level.


Desired end result:

deployment req1: 100 CAR going to DC1 for M1 and C1

deployment req2: 150 CAR going to DC1 for M1 and C2

deployment req3: 200 CAR going to DC1 for M1 and C3


Is this possible in APO using either SNP or PPDS using heuristics/CTM or optimizer?