Hello All,
We've this process chain that was running successfully until we made a small change.
Process chain when worked fine when it was in this state:
However, when we added another step in the process chain it is failing in version copy step every time it runs. The key observation is if see the log it shows that it has completed all the steps that would typically happen in version copy (so version copy is successful). However, the chain then ends in status 'R' and doesn't proceed further.
The reason the chain has completed is because I've 'skipped' the version copy step (knowing that version copy is successful). The process chain then completes successfully.
Here's the message from version copy step that fails every time.
Just to add, the last step that we added is a custom ABAP program that updates another process chain.
Any suggestions as to how to fix this?
Thanks a lot in advance for your inputs.
Best Regards,
Hiren