Do not want system to plan anything during gap period

$
0
0

Hi,

We have scenario where planning Gap is required for few months during the entire horizon for respective group of products.

e.g.

Say horizon is 1 year ( Jan to Dec. )

product A - > gap needed for July,Aug & Sep.  ( i.e. System can plan Jan to June and Oct-Dec but it should not plan anything during July to Sep)

Product B-> gap is June,July ( i.e. System can plan Jan to May and Aug-Dec but it should not plan anything during June and July )

Note:- we can receive Sales order as per customer order but will not plan and supply during these GAP period.

 

We thought of using Transportation Lane validity

e,g, for product A create two Lanes with different validity date.

TLane1 :- validity from 01-01-2015 till 30-June2015

Tlane 2:- Validity from 01-10-2015 till 31-12-2015

 

 

but SNP Heuristic is not respecting this ( it seems there is some flaw , might need to check sap note)

 

Please suggest

Thanks

Samir