We need to avoid rescheduling of Production order in APO

$
0
0

Currently the production orders are created in ECC with reference to the plan orders transferred from APO. These orders are transferred back to APO as part of standard CIF. Since ECC is the owner of Production orders, we don’t want APO influencing any changes in production order. But there are situations when the APO is rescheduling the production order by automatically triggering heuristics after getting the changes in capacity from ECC via CIF. That is impacting with the schedule of orders already planned by business in ECC. One such known issue is when the capacity of resource has change during the time when order is scheduled. How should we avoid this?