Back dated PReqs created in ECC

$
0
0

Hi Experts,

We have a situation where in the the PReqs in ECC are calculated in

past.

We have an example where by there was a requirement at C079 on 24th

February. There is GR Processing time of 5 days maintained at C079 and

transport duration of 24 minutes. After running deployment, a

Distribution Demand (Confirmed) was created on the source, C061 on 19th

February and a Distribution Receipt (Confirmed) was created on C079 for

24th Feb. This, we believe is as expected.

Now, in ECC we are able to see a PReq at C079 on 24th Feb, but the

corresponding PReq on C061 is showing on 2nd Feb in MD04. We need to

understand that as to why the PReq at C061 has been created in past.

Please note that there is a Planned Delivery Time of 17 days maintained

at C079. We understand that this should not cause any issue, but please

take a note of it.

Please advice. Thank you.

 

Regards,

Rishi