Hi Experts,

 

we have been facing an issue , when i run PPDS product heurestics manually in //RRP3 planned orders are getting created out of the PPDS horizon

 

PPDS Horizon- 120days

Lot size - periodic lot size 1 day

Product Heuristic - Planning of Standard Lots for Conti- I/O

Resource utilization - 100%

Resource availability - 12hrs.

Min lot size - 1000

Rounding  - 1000.

 

when we increase the Resource avialability or when we run it with Max lot size orders are getting created within PPDS horizon. but we cant change these things.

 

provided the Attachment

 

please provide your inputs

 

 

Thanks