Hi Experts,
I have a scenario where we have one FG (F1) with two assembly components S1 and S2 .Assembly components have their own routings.All the master data is exist in APO as well.An order is created for FG and dependent requirements are generated on assembly Components S1 and S2.Please see below to find the clear picture of routings and operations
In ECC
Operations for FG
Op3
Op4
Operations for S1
Op1
Operations for S2
Op2
We have four resources in Line 1 - R1,R2,R3 and R4
Line 2 - R11,R12,R13 and R14.
Operations are dispatched accordingly in routing.
Op1 - R1,Op2 - R2, Op3 - R3 and Op4 - R4
In APO
PDS created for S1,S2 and FG
Each having two different PDS consisting resources of Line 1 In PDS 1 and Line 2 in PDS 2
My requirements is when order is created against a requirement for FG then dependent requirments is generated for S1 and S2.After MRP run orders are created against dependent requirement.Now if i see the relationship for FG order in Ds Board I can see the dependent orders also.Since my op4 is a bottleneck resource, if there is not much capacity available to produce the order qty then I try to swtich the order from Resource R4 to Resource R14.I am just dragging the order from one resource to other resource but the problem is I want my S1 and S2 orders should also automatically move from R1 to R11 and R2 to R12.
For Finished good's order source of supply is changing but for Assembly components orders its is not changing automatically.Please provide some solution how I can achive this scenario in PPDS.