Hi Experts,
When Sales Orders are placed in the system, we execute the CTP process & have planned orders created immediately, using the Backward+Reverse planning direction. The planned orders are scheduled finitely on the resource & are created to meet their requirement dates at the earliest available time.
We want to be able to execute a function on the Planning board & "close the open gaps" on the schedule, that get left on there otherwise. Example, for the next month's schedule, we would not like any gaps on the schedule. We know that multiple orders could be drag/dropped on the planning board to achieve this, however, is there no automated way to get this done?
I tried the "Squeeze operation & Close gap" but that's not exactly what we want. We are looking to close gaps on the schedule for a month from the current time.
Any clue on how this could be achieved?
Thanks