Quantcast
Channel: SCN : Unanswered Discussions - Supply Chain Management (SAP SCM)
Viewing all articles
Browse latest Browse all 5579

object dependency in pl /prod orders in APO PP/DS (7.03)

$
0
0

Hi,

 

I am trying to find a solution for the below issue.

 

In the routing there are several operations maintained and there might be alternative routings or alternative work centers (classified) for one operation.

The idea is that when creating a planned order for a specific product and choosing a certain work center XY for operation 20, the system should know that the same work center has to be used for operation 40. I am looking for object dependency so the system would adjust the work center for operation 40 automatically based on work center being used for operation 20.

 

Any idea how this might be solved?

 

I thought of classiffing the work centers and operations and create object dependency in the routing...

 

 

thank you for any helpful input!

 

best regards,

Pilvi


Viewing all articles
Browse latest Browse all 5579

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>