Hi Gurus,
My SOs are placed against DC and it procures from Production Plant.
I have two SOs of same quantity (say 500kg each) of different dates at DC. There are two SNP Deployment PReqs of 500 each of different dates which procure from Production plant. But in Product view of DC when I select any of the two SO and go to pegging tab --I see it pegged to the same SNP Dep Preq. This is a bit confusing as each SO should be pegged to a different Dep PReq. ( Obviously one Dep Preq of 500 can not satisfy two SOs of 500 each !).
Can you please explain this behaviour ? I read somewhere that pegging in SNP is not reliable --which seems to be vary vague as otherwise SAP would not have provided pegging against SNP demand and supply elements.
Is there any other way of tracking (except pegging and dates) to see which SO is mapped to which Dep PReq? I need this information to track further the corresponding Planned order against Dep Preq.
Best Regards.
GIG SL