Experts,
I have a question regarding SNP Heuristics's
Here is the scenario
we have Product A and Product B
and we have BOM for Product A with Product B as component
Product B is Procured Item from supplier
Product A is subcontracted Item
once Product B is received from the supplier
it is send to vendor B for packing and Received as Product A
Now i am trying to figure out how to Planned delivery time and Minimum lot size and rounding value works
Product A is forecasting ITEM
For instance forecast QTy is 100
and SNP heuristics will create a PR for Product A (100) to pack to subcontracting vendor and another for Product B(100) to the supplier
now for product B i have lead time of 50 days to arrive , and have lot size of 120 and rounding value of 100
and for Product A lead time for packing is 3 days
now my question is
1) can i maintain all the PDT in product B level and leave Product A empty ?
2) do i need to maintain MOQ and rounding value in both product A and Product B ?
please take note what ever the product B i received from supplier i have to raise a PR to subcontracting vendor to pack it
to make it sample Product B i Received must be packed to Product A - 100 percent
hope my question too BIG appreciate if help to answer
Regards
Raj