Subcontracting PReq conversion

$
0
0

Hi All,

 

When I convert a subcontracting SNP- PReq at Plant then it creates an SNP PReqRel at vendor keeping in account PDT (Planned Delivery Time) , Transportation Time and GR time at Plant.

The SNP Planned Order created at vendor is created on the basis of backward scheduling.

( i.e. SNP Planned Order Completion date = Delivery Date at the Plant - Transportation Time - GR time

e.g.  SNP Planned Order Completion date( 10th Oct ) = Delivery Date at the Plant(17th Oct) - Transportation Time(4 days) - GR time ( 3 days)

Needless to say here -- SNP Planned Order finishes as per the time maintained in PPM/PDS for operation. ( e.g. say 4 days -- so it starts on 7th Oct). 

 

The issue comes when I convert this SNP Preq at plant to PPDS PReq.  The system schedules the order from current date or as soon as possible instead of doing backward scheduling. I checked the strategy profile in SPRO for SNP->PPDS conversion and in that strategy profile -- the direction for scheduling is forward.

As per me it should be backward or backward with reverse if I want the order to finish on 10th Oct as per example above.

This is bcoz between SNP and PPDS -- Transportation Time, GR time, PDT etc all remain same -- so I do not doubt the Master data.

 

Can you suggest some other pointer --- or  only the direction of scheduling in the strategy in strategy profile for SNP->PPDS conversion -- the only probable reason ?

 

 

Thanks.