Hello experts,
Scenario: APO characteristics planning with CDP class 400, discrete manufacturing. We would like to use SetUp matrix with characteristics. Supposing that we have the characteristic COLOR with values A,B,C,D,E and F (this is also the preferred sequence). PPDS optimizer is used to optimize the setup time.
After first run of PPDS optimizer the sequence is: A, B, D, A, E, B, C, F. We would like to keep the first two colors A and B and re-plan the others without taking in consideration A and B again.
How can I achieve this? Which kind of constraints/conditions can I use to exclude from the next PPDS optimizer run the two first colors (A, B) that were already scheduled?
The block planning with characteristics is not accepted by business (neither production campaign).
Any idea will be appreciated. Thanks.
Regards, Marius