Push Production functionality across many bom levels

Hi,

 

everyone who knows the push production functionality knows that we can select for a bom component the Products (PDS) in which this components goes in as a bom component.

 

example:

level 1: End Product: 1510

level 2:SF 1601 - bom component of 1510

level 3: SF 3201 - bom component of 1601

level 4: SF 7810 - bom component of 3201

level 5: raw material - 1001 - bom component of 7810

I am facing a situation with five bom levels. The planners often check the available qty of a component in the lowet bom level and based on that decide what qty of the end product (top level) they will produce. They do it currently in excel.

 

This looks like the push functionality but used for the lowest level to check the possible output qty of the top level, not the next one as it is possible in APO with the "push production". Looking at the example above this would be like entering the push production with raw material 7810 in order to check what qty of the end product 1510 can I produce based on the availabl eqty of the raw material 7810.

 

Question: is this somehow possible? is there any user exit / badi to enable such a check in push production?

 

Or should they use a different approach for this in APO?

 

thank for all useful hints!!!

 