Dear Gurus,
We are investigating the possibility to use Global ATP. An important requirement for us is that ATP can meet a specific
scenario which, from research, we cannot conclude whether Global ATP support this scenario:
Material 1 and other materials are entered for delivery from Plant A. We want it (complete) delivered from Plant A.
Material 1 is usually delivered from and at stock in Plant B.
In Plant A no ATP exists for material 1 and a stock transport order has to be/is created from Plant B.
The question is:
Does the confirmed delivery date to the customer for Plant A account for the ATP-situation in Plant B if there is
unexpectedly no stock at Plant B?
Or does the confirmed delivery date only accounts for the time getting the goods delivered from Plant B to Plant A.
Hope for an positive answer.
regards