Confirmed delivery date with Global ATP

Dear Gurus,

 

We are investigating the possibility to use Global ATP. An important requirement for us is that ATP can meet a specific
scenario which, from research, we cannot conclude whether Global ATP support this scenario:

 

Material 1 and other materials are entered for delivery from Plant A. We want it (complete) delivered from Plant A.
Material 1 is usually delivered from and at stock in Plant B.

 

In Plant A no ATP exists for material 1 and a stock transport order has to be/is created from Plant B.

 

The question is:

 

Does the confirmed delivery date to the customer for Plant A account for the ATP-situation in Plant B if there is
unexpectedly no stock at Plant B?

Or does the confirmed delivery date only accounts for the time getting the goods delivered from Plant B to Plant A.

 

Hope for an positive answer.

 