I want to schedule an order on a shift break. I want it to be forward scheduled so that the order starts after the shift break.
But the problem is, that only the P-Phase is scheduled after the break and the dynamic setup time is scheduled before the break and while the break (depends on pds settings of course).
Why is the scheduler not considering the setup phase while scheduling forward?
You can see it for example on DSPB with drag and drop, but also every heuristic is scheduling with this behaviour.
I'm thankful for every answer!
Thank you very much and best regards,
Florian